Notify Me Module Icon

Notify Me

  1. Type your email address in the box and select Sign In.
  2. If you want to receive text messages enter your phone number and select Save.
  3. To subscribe or unsubscribe click Email icon and/or SMS icon next to the lists to which you wish to subscribe/unsubscribe.
Available Lists
Sender Name:
2020 Mill and Overlay Project
Sent By:
(Automatically Sent By Website)
Send Date:
4/17/2020 6:19:51 AM
Email Subject:
2020 Mill and Overlay Project Update 04/17/2020

Formatted HTML message

Notify Me Banner
I hope everyone had a good week.  Work began on all phases of project this week.  Below is a breakdown of work performed this week, and a preview of the work proposed for next week for each individual phase.

Phase 1 - Jefferson Road and Heritage Drive
Removals crews were on-site mid-week to begin sawing concrete sidewalks, curbs and gutters, and driveway aprons that are scheduled for removal and replacement.  In addition, tree removal crews were on-site later in the week to perform the tree removals on all of Phase 1.  As a reminder, as discussed at the neighborhood meetings, crews will be removing all Ash trees with a diameter breast height (DBH) of 13" or under, and any other trees that were scored by a licensed arborist having a condition rating of 3 or less on a 0-9 condition rating scale.  In addition, there are a few trees slated for removal due to the construction project as well.

Next week, removal crews will begin removing concrete sidewalks, curbs and gutters, and driveway aprons on Phase 1.  Concrete crews are also scheduled to be on-site late in the week to begin pouring the replacement sidewalks, curbs and gutters and driveway aprons.  Please be on the lookout for notices left at your front door for important information on driveway access closures or construction operations that will specifically affect your property.  

Phase 2 - Seventh Street and Eighth Street
Removals crews were on-site mid-week to begin sawing concrete sidewalks, curbs and gutters, and driveway aprons that are scheduled for removal and replacement.  In addition, tree removal crews were on-site later in the week to perform the tree removals on all of Phase 2.  As a reminder, as discussed at the neighborhood meetings, crews will be removing all Ash trees with a diameter breast height (DBH) of 13" or under, and any other trees that were scored by a licensed arborist having a condition rating of 3 or less on a 0-9 condition rating.   In addition, there are a few trees slated for removal due to the construction project as well.
.


Next week, removal crews will begin removing concrete sidewalks, curbs and gutters, and driveway aprons on Phase 2.  Concrete crews are also scheduled to be on-site late in the week to begin pouring the replacement sidewalks, curbs and gutters and driveway aprons.  Please be on the lookout for notices left at your front door for important information on driveway access closures or construction operations that will specifically affect your property.  


Phase 3 - Carleton College East Area
Tree removal crews will be on-site today to perform the tree removals on all of Phase 3.  As a reminder, as discussed at the neighborhood meetings, crews will be removing all Ash trees with a diameter breast height (DBH) of 13" or under, and any other trees that were scored by a licensed arborist having a condition rating of 3 or less on a 0-9 condition rating.   In addition, there are a few trees slated for removal due to the construction project as well.

Next week, removal crews will be on-site to begin saw-cutting concrete sidewalks, curbs and gutters, and driveway aprons that are scheduled for removals.  No other work is scheduled on Phase 3 next week.


Phase 4 - Carleton College West Area
Tree removal crews will be on-site today to perform the tree removals on all of Phase 4.  As a reminder, as discussed at the neighborhood meetings, crews will be removing all Ash trees with a diameter breast height (DBH) of 13" or under, and any other trees that were scored by a licensed arborist having a condition rating of 3 or less on a 0-9 condition rating.  Also, there are a few trees slated for removal due to the construction as well.

Next week, removal crews will be on-site to begin saw-cutting concrete sidewalks, curbs and gutters, and driveway aprons that are scheduled for removals.  No other work is scheduled on Phase 4 next week.


For additional information regarding the project, please visit the Project website:
https://www.ci.northfield.mn.us/1313/2020-Mill-and-Overlay-Project

Questions/Concerns?
Brian Schmit with Bolton and Menk is the Resident Project Representative.  Brian can be reached at:

brian.schmit@bolton-menk.com
612-368-1228

Thanks! 

   

Plain text message

I hope everyone had a good week. Work began on all phases of project this week. Below is a breakdown of work performed this week, and a preview of the work proposed for next week for each individual phase.

Phase 1 - Jefferson Road and Heritage Drive
Removals crews were on-site mid-week to begin sawing concrete sidewalks, curbs and gutters, and driveway aprons that are scheduled for removal and replacement. In addition, tree removal crews were on-site later in the week to perform the tree removals on all of Phase 1. As a reminder, as discussed at the neighborhood meetings, crews will be removing all Ash trees with a diameter breast height (DBH) of 13" or under, and any other trees that were scored by a licensed arborist having a condition rating of 3 or less on a 0-9 condition rating scale. In addition, there are a few trees slated for removal due to the construction project as well.

Next week, removal crews will begin removing concrete sidewalks, curbs and gutters, and driveway aprons on Phase 1. Concrete crews are also scheduled to be on-site late in the week to begin pouring the replacement sidewalks, curbs and gutters and driveway aprons. Please be on the lookout for notices left at your front door for important information on driveway access closures or construction operations that will specifically affect your property.

Phase 2 - Seventh Street and Eighth Street
Removals crews were on-site mid-week to begin sawing concrete sidewalks, curbs and gutters, and driveway aprons that are scheduled for removal and replacement. In addition, tree removal crews were on-site later in the week to perform the tree removals on all of Phase 2. As a reminder, as discussed at the neighborhood meetings, crews will be removing all Ash trees with a diameter breast height (DBH) of 13" or under, and any other trees that were scored by a licensed arborist having a condition rating of 3 or less on a 0-9 condition rating. In addition, there are a few trees slated for removal due to the construction project as well.

Next week, removal crews will begin removing concrete sidewalks, curbs and gutters, and driveway aprons on Phase 2. Concrete crews are also scheduled to be on-site late in the week to begin pouring the replacement sidewalks, curbs and gutters and driveway aprons. Please be on the lookout for notices left at your front door for important information on driveway access closures or construction operations that will specifically affect your property.

Phase 3 - Carleton College East Area
Tree removal crews will be on-site today to perform the tree removals on all of Phase 3. As a reminder, as discussed at the neighborhood meetings, crews will be removing all Ash trees with a diameter breast height (DBH) of 13" or under, and any other trees that were scored by a licensed arborist having a condition rating of 3 or less on a 0-9 condition rating. In addition, there are a few trees slated for removal due to the construction project as well.

Next week, removal crews will be on-site to begin saw-cutting concrete sidewalks, curbs and gutters, and driveway aprons that are scheduled for removals. No other work is scheduled on Phase 3 next week.


Phase 4 - Carleton College West Area

Tree removal crews will be on-site today to perform the tree removals on all of Phase 4. As a reminder, as discussed at the neighborhood meetings, crews will be removing all Ash trees with a diameter breast height (DBH) of 13" or under, and any other trees that were scored by a licensed arborist having a condition rating of 3 or less on a 0-9 condition rating. Also, there are a few trees slated for removal due to the construction as well.

Next week, removal crews will be on-site to begin saw-cutting concrete sidewalks, curbs and gutters, and driveway aprons that are scheduled for removals. No other work is scheduled on Phase 4 next week.

For additional information regarding the project, please visit the Project website:
https://www.ci.northfield.mn.us/1313/2020-Mill-and-Overlay-Project

Questions/Concerns?
Brian Schmit with Bolton and Menk is the Resident Project Representative. Brian can be reached at:

brian.schmit@bolton-menk.com
612-368-1228

Thanks!