Notify Me Module Icon

Notify Me

  1. Type your email address in the box and select Sign In.
  2. If you want to receive text messages enter your phone number and select Save.
  3. To subscribe or unsubscribe click Email icon and/or SMS icon next to the lists to which you wish to subscribe/unsubscribe.
Available Lists
Sender Name:
2020 Mill and Overlay Project
Sent By:
(Automatically Sent By Website)
Send Date:
4/10/2020 2:04:53 PM
Email Subject:
2020 Mill and Overlay Project Update 04/10/2020

Formatted HTML message

Notify Me Banner
Staff held the "Preconstruction Conference" with McNamara Contracting this week.  McNamara submitted their schedule for all four project phases.  Below is a breakdown and schedule for each project phase.

Phase 1 - Jefferson Road and Heritage Drive
Phase 1 includes Jefferson Road from Hidden Valley Road to Heritage Drive, and Heritage Drive from TH 3 to Hidden Valley Drive.  Phase 1 is expected to begin on April 16, 2020, and be completed by mid-May.  Below is a list of major construction activities proposed on Phase 1:
  • Tree removals
  • Storm sewer installations
  • Concrete curb and gutter and sidewalk removals
  • Concrete curb and gutter and sidewalk installations
  • Boulevard restoration, sod placement and tree planting
  • Pavement milling and patching
  • Pavement “Wear Course” installation
  • Pavement striping and sign installations
Next week, crews expect to be on-site late in the week to complete the tree removals on all of Phase 1.

Phase 2 - Seventh Street and Eighth Street
Phase 2 includes Seventh Street from Water Street to Riverside Park, and Eighth Street from Water Street to Linden Street.  Phase 2 is expected to begin on April 16, 2020, and completed by late May.  Below is a list of major construction activities proposed on Phase 2:
  • Tree removals
  • Storm sewer installations
  • Cul-de-sac installation on Seventh Street
  • Concrete curb and gutter and sidewalk removals
  • Concrete curb and gutter and sidewalk installations
  • Boulevard restoration, sod placement and tree planting
  • Pavement “Base Course” installation on the Seventh Street Cul-de-sac
  • Pavement milling and patching
  • Pavement “Wear Course” installation
  • Pavement striping and sign installations
Next week, crews expect to be on-site late in the week to complete the tree removals on all of Phase 2.

Phase 3 - Carleton College East Area
Phase 3 includes the eastern half of the Carleton College project area.  Please refer to the website listed below for the Phase map for the street sections included in Phase 3.  Phase 3 is scheduled to begin April 16, 2020 and be completed by early June.  Below is a list of major construction activities proposed on Phase 3:
  • Tree removals
  • Storm sewer installations
  • Concrete curb and gutter and sidewalk removals
  • Concrete curb and gutter and sidewalk installations
  • Boulevard restoration, sod placement and tree planting
  • Pavement milling and patching
  • Pavement “Wear Course” installation
  • Pavement striping and sign installations
Next week, crews expect to be on-site late in the week to begin tree removals on all of Phase 3.  Crews expect to complete the tree removals on phase 3 during the week of April 20th.

Phase 4 - Carleton College West Area
Phase 4 includes the western half of the Carleton College project area.  Please refer to the website listed below for the Phase map for the street sections included in Phase 4.  Phase 4 is scheduled to begin May 18, 2020 and be completed by mid-July.  Below is a list of major construction activities proposed on Phase 3:
  • Tree removals
  • Storm sewer installations
  • Concrete curb and gutter and sidewalk removals
  • Concrete curb and gutter and sidewalk installations
  • Boulevard restoration, sod placement and tree planting
  • Pavement milling and patching
  • Pavement “Wear Course” installation
  • Pavement striping and sign installations
Next week, crews expect to be on-site late in the week to begin tree removals on all of Phase 4.  Crews expect to complete the tree removals on phase 4 during the week of April 20th.  No other work on Phase 4 is scheduled until mid-May.

Staff also mailed out a newsletter late this week, which contains a more detailed breakdown of the project schedule for each phase listed above, and a phasing map.  This information is also included on the project website:

https://www.ci.northfield.mn.us/1313/2020-Mill-and-Overlay-Project

Thanks!

City of Northfield Engineering Division

801 Washington Street
Northfield, MN
(507) 645-3049
Sean.Simonson@ci.northfield.mn.us

   

Plain text message

Staff held the "Preconstruction Conference" with McNamara Contracting this week. McNamara submitted their schedule for all four project phases. Below is a breakdown and schedule for each project phase.

Phase 1 - Jefferson Road and Heritage Drive
Phase 1 includes Jefferson Road from Hidden Valley Road to Heritage Drive, and Heritage Drive from TH 3 to Hidden Valley Drive. Phase 1 is expected to begin on April 16, 2020, and be completed by mid-May. Below is a list of major construction activities proposed on Phase 1:
Tree removals
Storm sewer installations
Concrete curb and gutter and sidewalk removals
Concrete curb and gutter and sidewalk installations
Boulevard restoration, sod placement and tree planting
Pavement milling and patching
Pavement “Wear Course” installation
Pavement striping and sign installations
Next week, crews expect to be on-site late in the week to complete the tree removals on all of Phase 1.

Phase 2 - Seventh Street and Eighth Street

Phase 2 includes Seventh Street from Water Street to Riverside Park, and Eighth Street from Water Street to Linden Street. Phase 2 is expected to begin on April 16, 2020, and completed by late May. Below is a list of major construction activities proposed on Phase 2:
Tree removals
Storm sewer installations
Cul-de-sac installation on Seventh Street
Concrete curb and gutter and sidewalk removals
Concrete curb and gutter and sidewalk installations
Boulevard restoration, sod placement and tree planting
Pavement “Base Course” installation on the Seventh Street Cul-de-sac
Pavement milling and patching
Pavement “Wear Course” installation
Pavement striping and sign installations
Next week, crews expect to be on-site late in the week to complete the tree removals on all of Phase 2.

Phase 3 - Carleton College East Area
Phase 3 includes the eastern half of the Carleton College project area. Please refer to the website listed below for the Phase map for the street sections included in Phase 3. Phase 3 is scheduled to begin April 16, 2020 and be completed by early June. Below is a list of major construction activities proposed on Phase 3:
Tree removals
Storm sewer installations
Concrete curb and gutter and sidewalk removals
Concrete curb and gutter and sidewalk installations
Boulevard restoration, sod placement and tree planting
Pavement milling and patching
Pavement “Wear Course” installation
Pavement striping and sign installations
Next week, crews expect to be on-site late in the week to begin tree removals on all of Phase 3. Crews expect to complete the tree removals on phase 3 during the week of April 20th.

Phase 4 - Carleton College West Area
Phase 4 includes the western half of the Carleton College project area. Please refer to the website listed below for the Phase map for the street sections included in Phase 4. Phase 4 is scheduled to begin May 18, 2020 and be completed by mid-July. Below is a list of major construction activities proposed on Phase 3:Tree removals
Storm sewer installations
Concrete curb and gutter and sidewalk removals
Concrete curb and gutter and sidewalk installations
Boulevard restoration, sod placement and tree planting
Pavement milling and patching
Pavement “Wear Course” installation
Pavement striping and sign installations
Next week, crews expect to be on-site late in the week to begin tree removals on all of Phase 4. Crews expect to complete the tree removals on phase 4 during the week of April 20th. No other work on Phase 4 is scheduled until mid-May.

Staff also mailed out a newsletter late this week, which contains a more detailed breakdown of the project schedule for each phase listed above, and a phasing map. This information is also included on the project website:

https://www.ci.northfield.mn.us/1313/2020-Mill-and-Overlay-Project

Thanks!

City of Northfield Engineering Division